Project Name: QP-SHELL-Pearl Gas to Liquids (GTL) Project
Name of Client: QP/Shell International Gas Ltd
Budget (US$): 6,000,000,000
Main Contractor: Not yet appointed
Facility Type: Gas to Liquids Conversion
Status: EPC Bid Submission
PMC: JGC / Kellog Brown & Root
Location: Messaieed/Ras Laffan
Project Status
A statement of intent was signed between Qatar Petroleum (QP) and Shell International Gas Limited in February 2002 to study the development of a gas-to-liquids (GTL) facility. The gas feedstock for this would be supplied from the ongoing upstream development of the North Field. Shell is also looking to include the upstream development into the project.
In addition to GTL products, the project will also produce substantial quantities of associated upstream products in the form of condensate and natural gas liquids (NGLs) such as liquefied petroleum gas (LPG).
Shell plans to invest in offshore facilities and an onshore plant that produces 140,000 barrels per day (bpd) of GTL products (primarily naphtha and transport fuels, with smaller quantities of normal paraffin and lubricant base oils), and associated condensate and LPG.
The project will be developed in two phases with the first phase operational in 2009, producing around 70,000 bpd of GTL products. The second phase will be completed less than two years later.
Progress has already been made offshore with seismic acquisition of the vast North Field and the first of two appraisal wells has been drilled to confirm gas compositions. The Front End Engineering and Design phase (FEED) phase has started which will require almost half a million man hours.
A heads of agreement (HOA) was signed in October 2003 between Qatar Petroleum and Qatar Shell GTL for the construction of what will be the world’s largest GTL plant.
The $6 billion investment will not only cover the construction of 140,000 bpd GTL plant but also the development of a dedicated block in the North Field that will produce 1.6 BSCFD of gas as feedstock for the project.
In December 2004, 70 per cent of the onshore FEED and 90 per cent of the offshore FEED was completed.
In early March 2005, Honeywell Process Solutions was awarded the FEED contract for the plant automation. This comprised the complete plant automation systems, including onshore and offshore portions.
Prequalifications were due to be submitted in mid-July 2005 for five onshore packages on the estimated $6,000 million Pearl (GTL) project at Ras Laffan. The packages cover the following: air separation units, storage tanks, gas treatment plant, liquid processing unit, water treatment.
Platform Package (Offshore)
Shell had originally proposed awarding just one EPC contract covering the entire onshore works, but chose the packaged approach to increase contractor competition.
About 45 international companies were invited to pre-qualify for the five onshore EPC lumpsum packages.
Several other onshore packages will be awarded on the project, of which two, covering the core elements, may be placed on an engineering, procurement and construction management (EPCM) basis. The first train is due to come on stream in 2009 and the second is scheduled for completion two years later.
In July 2005, a tender for two offshore engineering, procurement and construction (EPC) packages was released.
In mid-September 2005, a letter of intent was issued to the JV of KBR and JGC for PMC contract.
In early October 2005, tenders for the feedgas processing facilities and liquid processing unit were issued.
The following contractors are prequalified for the Onshore portion: Hyundai, Petrofac, Snamprogetti, Technip / Chiyoda, Toyo Engineering, Washington Group.
A contract award is likely in mid-2006.
Bids for the material offloading facility were due in November 2005. In early October 2005, tenders for the C4 & C5 onshore packages were released. Technical bid closing date for C1 is December 1 and commercial bid submission is believed to be on February 26, 2006. Technical bids for C2 are due on January 4, 2006 and commercial bids are due on February 23, 2006. Bids are also due in February 2006 for the Water Treatment Plant package (C8).
Project Scope
Qatar’s North Field is the worlds largest natural gas accumulation, with reserves of over 900 trillion cubic feet. The strong interest being shown by Qatar in GTL conversion projects is based upon the potential markets for ultra clean products for which there is a growing demand.
Shell would offer its proprietary Middle Distillates Synthesis (SMDS) technology. This is currently being used in its Bintulu facility in Malaysia. This is part of an overall Shell strategy to produce a portfolio of second generation GTL projects worldwide.
The project will be developed in two phases with the first phase operational between 2008-9. Shell are provisionally looking at a facility with two trains that would produce 70-75,000 bpd each. Over a 20-25 year period some 5 TSCF of gas would be required as feedstock. This would make it the largest gas to liquids plant in the world. Initially only one train would be built.
A third train could be added at a later date to increase the total capacity to 210,000 bpd.
For each offshore phase of the project there will be a simple, unmanned wellhead platform for gas production. These will have no processing equipment and the fluids will be transported to shore through multiphase 28 inch pipelines. The pipelines will be carbon steel so corrosion control is critical.
The onshore plant will treat the rich, sour gas to produce LPG, condensate and, at a later stage, ethane together with the dry, sweet and lean gas to feed the 140,000 barrel a day GTL process. As well as the core products naphtha and gasoil the plant will also produce n-paraffins and lubricant base oils.
